Building Access Key Location
Upon the delivery of your building, ask the driver for your paperwork and key. The key should be included with the pack list.
Electrical Installation
A UL-Listed Load Center (NEMA 3R) with appropriate circuit breakers will supplied to any building that has electrical components. Each building will also be supplied with a static electricity grounding kit.
The kit consists of the following:
- Building Ground Lug (attached to base)
- Grounding Electrode with Lug (8 or l0 feet)
Site Grounding Techniques
Grounding Your Storage Building
NOTE: Your grounding rod is attached to the steel grate flooring during shipment of your chemical building.
- To reduce the risk of shock to site personnel, all metal buildings need to be grounded. To properly ground a structure, penetrate the earth adjacent to the building with the grounding rod. Use a 10-gauge copper conductor wire to then connect the rod to the building.
- Each container should then be grounded individually using the same wire. The containers should be grounded to the interior lugs located in the corners of the building.
- Additional connections should be provided between containers if you are dispensing throughout the building. This can be done with the Gator clips and copper conductor wire. A conductor wire should be used to connect each container to a grounded lug.
If you have additional questions regarding the grounding of the building, please call a licensed electrician.